Building Speed: Labor Day Prep and Paneling Success
This week on Sunchaser’s we began the week with labor day which cut our crew size down to 5, and as a result we spent most of the day getting measurements for wiring as well as the substation that we will be installing. Aside from that, the rest of the week was relatively standard. Both crews are paneling at a relatively quick rate. September fifth we were able to install over 300 panels which is certainly exciting. Aside from that we are working remarkably well.